2018 Heavy Commercial (Religious)
Best in Class

Project Statistics


Location: Chandler, Arizona
Type: Catholic Church
Size: 22,536 sq. ft. (floor)
ICF Use: 41,429 sq. ft.
Cost: $7.2 million
Total Construction: 68 weeks
ICF Installation Time: 76 days

 

Construction Team


Owner: Phoenix Diocese
General Contractor: Chasse Building Team
ICF Installer + Form Distributor: ICF Specialist
Architect: Phoenix Design Group
ICF System: Fox Blocks

Fast Facts


Tall radius walls and arched windows
18 elevation variations
670 embeds placed
Solid foam block outs reused for many arches
Numerous visitors and industry presentations

 

 